Kondisi Pembangkit PLTU Baturaja 1 Juni 2023
Kondisi Operasi Mesin
STG 1 = OFF
STG 2 = ON (24 Jam)
Kondisi Maintenance
Progres Overhaul hari ke 5
| Pekerjaan | Progress |
| A. Boiler 1 | 100% |
| Stop Boiler (100%) | 100% |
| Cooling Booiler, ESP, drain debu Esp 1 (100%) | 100% |
| Cleaning Esp 1 (100%) | 100% |
| Pengecekan Isolator dan Heater Esp 1 (75%) | 100% |
| Pengecekan dan perbaikan Collcecting Plate dan Elektroda Boiler 1 | Proses |
| Perbaikan kebocoran Ducting dan Bracing Esp 1 (15%) | 40% |
| Cleaning Air Heater Boiler 1 | Proses |
| Penggantian Shaft Rapping Vesel 1 | Proses |
| Penggantian Thermocouple Combution Boiler 1 | Proses |
| Pengecekan dan penggantian valve Collection Header Boiler 1 DN 80 & DN 20 | Proses |
| Pengecekan (perbaikan) sensor level drum Boiler 1 | Proses |
| Cleaning Burner Boiler 1 100% | 100% |
| Cleaning nozle Furnice Boiler 1 (70%) | 70% |
| Cleaning Nozle Solar Boiler 1 | Proses |
| Start Up Boiler 1 | Proses |
| B. Turbine 1 | |
| Stop Turbine 1 (100%) | 100% |
| Pengecekan Oli Governoor (50%) | 50% |
| Pengecekan Steam Room Governoor | 25% |
| Perbaikan sensor error di monitor CCR | 40% |
| Pengecekan (penggantian) Bearing Front Rear Turbine dan Generator (10%) | 45% |
| Set Aligment Shaft dan Coupling Turbine Generator | Proses |
| Perbaikan Flange gasket HPH Turbine 1 | Proses |
| Perbaikan pipa Drain main Steam Turbine 1 | Proses |
| Cleaning Condensore 1 (10%) | 10% |
| Cleaning Air Cooler 1 & 2 (100%) | 100% |
| Pengecekan dan Penggantian Bearing motor Exhaust Fan Turbine 1 | Proses |
| Pengecekan Generator STG 1 | Proses |
| Pengecekan Trafo STG 1 | Proses |
| Start Up Turbine 1 | Proses |
SPB
-SPB tgl 31 mei 2023 No : 009/V/OPS (MPB)Karung @20kg 200 pcs (Utk stok pasir Boiler 1 2)
Foto Kegiatan