Kondisi Operasi Mesin
STG 1 = OFF 24 jam
STG 2 = OFF 24 jam

Kondisi Maintenance

Progres Overhaul hari ke 12

PekerjaanProgress
A. Boiler 1100%
Stop Boiler (100%)100%
Cooling Booiler, ESP, drain debu Esp 1 (100%)100%
Cleaning Esp 1 (100%)100%
Pengecekan Isolator dan Heater Esp 1 (75%)100%
Pengecekan dan perbaikan Collcecting Plate dan Elektroda Boiler 175%
Perbaikan kebocoran Ducting dan Bracing Esp 1 (15%)100%
Cleaning Air Heater Boiler 1100%
Penggantian Shaft Rapping Vesel 1100%
Penggantian Thermocouple Combution Boiler 1100%
Pengecekan dan penggantian valve Collection Header Boiler 1 DN 80 & DN 20Proses
Pengecekan (perbaikan) sensor level drum Boiler 1100%
Cleaning Burner Boiler 1 100%100%
Cleaning nozle Furnice Boiler 1 (70%)100%
Cleaning Nozle Solar Boiler 1100%
Start Up Boiler 1Proses
B. Turbine 1
Stop Turbine 1 (100%)100%
Pengecekan Oli Governoor (50%)85%
Pengecekan Steam Room Governoor85%
Perbaikan sensor error di monitor CCR100%
Pengecekan (penggantian) Bearing Front Rear Turbine dan Generator (10%)100%
Set Aligment Shaft dan Coupling Turbine Generator100%
Perbaikan Flange gasket HPH Turbine 1100%
Perbaikan pipa Drain main Steam Turbine 1100%
Cleaning Condensore 1 (10%)90%
Cleaning Air Cooler 1 & 2 (100%)100%
Pengecekan dan Penggantian Bearing motor Exhaust Fan Turbine 1100%
Pengecekan Generator STG 190%
Pengecekan Trafo STG 1Proses
Start Up Turbine 1Proses
C. Common
Pengecekan (perbaikan) Bak Reservoir 2 & 3 (bocor/rembes)80%
Pengecekan (perbaikan) Corrosion Plate deck dan Handrill Cooling Tower30%
Pengecekan (perbaikan) System Sedimentasi70%
Perbaikan UPS100%
Perbaikan dan penggantian valve discharge main ash silo25%
Penggantian Filter udara Ash Silo100%
Perbaikan Mulut Hopper CrusherProses
Penggantian Belt Conveyor # 3100%
Perbaikan Drive Pully Belt conveyor #2100%
D. BOILER 2
Stop Boiler 2100%
Cooling Booiler, ESP, drain debu Esp 1100%
Cleaning Esp 140%
Pengecekan Isolator dan Heater Esp 1Proses
Pengecekan dan perbaikan Collcecting Plate dan Elektroda Boiler 1Proses
Perbaikan kebocoran Ducting dan Bracing Esp 1Proses
Cleaning Air Heater Boiler 1Proses
Repair flange gasket Front DesuperheaterProses
Pengecekan dan Penggantian valve collection header boiler 2 DN 80 & DN 20Proses
Penggantian shaft rapping Vesel 4100%
Repair Valve (Manual) Steam Blow Boiler 2Proses
Pengecekan (perbaikan) sensor level Drum boilerProses
Cleaning Burner Boiler 2Proses
Cleaning nozle Furnice Boiler 2Proses
Cleaning Nozle Solar Boiler 2Proses
Start Up Boiler 1Proses
E. Turbine 2
Stop Turbine 2100%
Pengecekan Oli GovernoorProses
Pengecekan Steam Room GovernoorProses
Perbaikan sensor error di monitor CCRProses
Pengecekan (penggantian) Bearing Front Rear Turbine dan GeneratorProses
Set Aligment Shaft dan Coupling Turbine GeneratorProses
Perbaikan kebocoran MOV Turbine 2 di Elv 11,5Proses
Cleaning Condensore 290%
Cleaning Air Cooler 1 & 2100%
Pengecekan dan Penggantian Bearing motor Exhaust Fan Turbine 2Proses
Pengecekan Generator STG 1 *Proses
Pengecekan Trafo STG 1Proses
Start Up Turbine 1Proses

SPB