Kondisi Pembangkit PLTU Baturaja 16 Juni 2023

Kondisi Operasi Mesin
STG 1 = ON 24 jam
STG 2 = OFF (0-11)

Kondisi Maintenance
Progres Overhaul hari ke 19

PekerjaanProgress
A. Boiler 1100%
Stop Boiler (100%)100%
Cooling Booiler, ESP, drain debu Esp 1 (100%)100%
Cleaning Esp 1 (100%)100%
Pengecekan Isolator dan Heater Esp 1 (75%)100%
Pengecekan dan perbaikan Collcecting Plate dan Elektroda Boiler 1100%
Perbaikan kebocoran Ducting dan Bracing Esp 1 (15%)100%
Cleaning Air Heater Boiler 1100%
Penggantian Shaft Rapping Vesel 1100%
Penggantian Thermocouple Combution Boiler 1100%
Pengecekan dan penggantian valve Collection Header Boiler 1 DN 80 & DN 20Proses
Pengecekan (perbaikan) sensor level drum Boiler 1100%
Cleaning Burner Boiler 1 100%100%
Cleaning nozle Furnice Boiler 1 (70%)100%
Cleaning Nozle Solar Boiler 1100%
Start Up Boiler 1100%
B. Turbine 1
Stop Turbine 1 (100%)100%
Pengecekan Oli Governoor (50%)100%
Pengecekan Steam Room Governoor100%
Perbaikan sensor error di monitor CCR100%
Pengecekan (penggantian) Bearing Front Rear Turbine dan Generator (10%)100%
Set Aligment Shaft dan Coupling Turbine Generator100%
Perbaikan Flange gasket HPH Turbine 1100%
Perbaikan pipa Drain main Steam Turbine 1100%
Cleaning Condensore 1 (10%)100%
Cleaning Air Cooler 1 & 2 (100%)100%
Pengecekan dan Penggantian Bearing motor Exhaust Fan Turbine 1100%
Pengecekan Generator STG 1100%
Pengecekan Trafo STG 1100%
Start Up Turbine 1100%
C. Common
Pengecekan (perbaikan) Bak Reservoir 2 & 3 (bocor/rembes)100%
Pengecekan (perbaikan) Corrosion Plate deck dan Handrill Cooling Tower42%
Pengecekan (perbaikan) System Sedimentasi100%
Perbaikan UPS100%
Perbaikan dan penggantian valve discharge main ash silo100%
Penggantian Filter udara Ash Silo100%
Perbaikan Mulut Hopper CrusherProses
Penggantian Belt Conveyor # 3100%
Perbaikan Drive Pully Belt conveyor #2100%
D. BOILER 2
Stop Boiler 2100%
Cooling Booiler, ESP, drain debu Esp 1100%
Cleaning Esp 1100%
Pengecekan Isolator dan Heater Esp 1100%
Pengecekan dan perbaikan Collcecting Plate dan Elektroda Boiler 1100%
Perbaikan kebocoran Ducting dan Bracing Esp 1100%
Cleaning Air Heater Boiler 1100%
Repair flange gasket Front Desuperheater100%
Pengecekan dan Penggantian valve collection header boiler 2 DN 80 & DN 20Proses
Penggantian shaft rapping Vesel 4100%
Repair Valve (Manual) Steam Blow Boiler 2100%
Pengecekan (perbaikan) sensor level Drum boiler100%
Cleaning Burner Boiler 2100%
Cleaning nozle Furnice Boiler 2100%
Cleaning Nozle Solar Boiler 2100%
Start Up Boiler 1Proses
E. Turbine 2
Stop Turbine 2100%
Pengecekan Oli Governoor100%
Pengecekan Steam Room Governoor100%
Perbaikan sensor error di monitor CCR100%
Pengecekan (penggantian) Bearing Front Rear Turbine dan Generator100%
Set Aligment Shaft dan Coupling Turbine Generator100%
Perbaikan kebocoran MOV Turbine 2 di Elv 11,5Proses
Cleaning Condensore 2100%
Cleaning Air Cooler 1 & 2100%
Pengecekan dan Penggantian Bearing motor Exhaust Fan Turbine 2100%
Pengecekan Generator STG 1 *90%
Pengecekan Trafo STG 1100%
Start Up Turbine 1100%