Kondisi Pembangkit PLTU Baturaja 27 Juli 2023
Kondisi Operasi Mesin
STG 1 = ON 24 jam
STG 2 = ON 24 jam
Maintenance
Mekanik
- Lubrication pully belt #2 saat stop running
- Mulai pabrikasi pipa jalur ke workshop baru
- Kontinue potong rondbar
- Kontinue repair FWP#3
- Lubrication bering CWP pump
- Daily maintenance & repair
Elektrik
- Chek inverter robot pasir(fkhu)
- continue instalasi lighting workshop
- Chek kabel out Cctv steam drum#2 ke ccr
- daily maintenance
SPB
Nihil
LAPORAN PROGRESS PEKERJAAN COOLING TOWER
Kanis, 27 Juli 2023
Pekerjaan per hari Rabu, 26 Juli 2023
Customer PLTU Baturaja – Sumatra Selatan
Objek Pekerjaan tahap 1. Cooling Tower Unit No 3
| Scope Of Work Mobilisasi dan demobilisasi Alat alat kerja (100%) Mobilisasi on site accomodasi power (97%) Performace Tools dam Welding test (100%) Pembongkaran rangka besi U 2 batang catwalk (100%) Fabrikasi dan cat dasar rangka besi U 2 batang catwalk (100%) Pemasangan rangka besi U 2 buah batang catwalk (100%) Finishing cat rangka besi U 2 buah batang catwalk (100%) Pembongkaran rangka catwalk, 12 rangka dari 12 rangka, (100%) Fabrikasi rangka catwalk 12 rangka dari 12 buah rangka, (100%) Pengecatan dasar rangka catwalk 12 rangka (100%) Pemasangan rangka catwalk 12 rangka (100%) Finishing cat rangka catwalk 12 buah rangka, (0%) Pembongkaran ralling pagar catwalk (100%) Fabrikasi ralling pagar catwalk (50%) Pengecatan dasar ralling pagar catwalk (50%) Pemasangan ralling pagar catwalk (50%) Finishing cat ralling pagar catwalk (0%) Fabrikasi ralling pagar (100%) Pembongkaran ralling pagar luar (100%) Pemasangan ralling pagar luar (100%) Pengecatan dasar ralling pagar luar (100%) Finishing cat ralling pagar (0%) Pengecatan dasar lantai bordes 70 lembar dari estimate 70 lembar (100%) Pembongkaran lantai bordes 70 lembar dari estimate 70 lembar (100%) Rekondisi dan pengecatan dasar rangka lantai bordes (85%) Setting bordes 45 lembar lantai bordes estimate 70 lembar (60%) Pengelasan lantai bordes estimate 70 lembar (10%) Finishing cat lantai bordes (0%) Pembongkaran tiang pipa (3mtr) breeching horizontal 1,5” 2 batang (100%) Fabrikasi dan cat dasar tiang pipa (3mtr) breeching horizontal 1,5” 12 batang (100%) Pemasangan tiang pipa breeching (3mtr) horizontal 1,5” 12 batang (100%) Finishing cat tiang pipa breeching (3mtr) horizontal 1,5” 12 batang dari 12 batang (75%) Pembongkaran tiang pipa (3,5mtr) breeching horizontal 1,5” 12 batang (100%) Fabrikasi dan cat dasar tiang pipa (3,5mtr) breeching horizontal 1,5” 12 btang (100%) Pemasangan tiang pipa breeching (3,5mtr) horizontal 1,5” 12 batang (100%) Finishing cat tiang pipa breeching (3,5mtr) horizontal 1,5” 12 batang (100%) Pembongkaran tiang pipa (3,5mtr) breeching vertikal 3” 4 batang (100%) Fabrikasi dan cat dasar tiang pipa (3,5mtr) breeching vertikal 3” 4 batang (100%) Pemasangan tiang pipa (3,5mtr) breeching vertikal 3” 4 batang (100%) Finishing cat dasar tiang pipa (3,5mtr) breeching vertikal 3” 4 batang (100%) Pembongkaran tiang pipa breeching (6mtr) diagonal 1,5” 12 batang (100%) Pemasangan tiang pipa bries (6mtr) diagonal 1,5” 12 batang (100%) Pengecatan dasar tiang pipa breeching (6mtr) diagonal 1,5” 12 batang (100%) Finishing cat tiang pipa breeching (6mtr) diagonal 1,5” 12 batang (75%) Pengangkatan drift eliminator keluar (100%) Rekondisi drift eliminator (100%) Pemasangan drift eliminator (0%) Pembersihan karat pipa penyangga utama dan lantai bordes area kerja |
Pekerjaan hari Rabu, 26 Juli 2023
• Pembongkaran lantai bordes lanjutan
• Pemasangan ralling pagar lanjutan
• Pengecatan dasar ralling pagar lanjutan
• Seting dan pemasangan bordes lanjutan
• Perbaikan rangka bordes dan finishing cat rangka bordes lanjutan
• Pemasangan ralling catwalk lanjutan
• Pembersihan area kerja dari debu dan serpihan besi dan karat bordes
Rencana Pekerjaan hari Kamis, 27 Juli 2023
• Pembongkaran dan perapihan lantai bordes lanjutan
• Setting dan pemasangan lantai bordes lanjutan
• Pemasangan ralling pagar lanjutan
• Pengecatan rangka grill catwalk lanjutan
• Pemasangan ralling catwalk lanjutan
• Perbaikan rangka bordes dan finishing rangka bordes lanjutan
• Setting, pemasangan dan pengelasan lantai dordes lanjutan
• Pengecatan pipa-pipa breeching dan dudukan drift lanjutan
• Pembersihan area kerja dari debu dan serpihan besi dan karat bordes