Kondisi Pembangkit PLTU Baturaja 27 Juli 2023

Kondisi Operasi Mesin
STG 1 = ON 24 jam
STG 2 = ON 24 jam

Maintenance

Mekanik

  1. Lubrication pully belt #2 saat stop running
  2. Mulai pabrikasi pipa jalur ke workshop baru
  3. Kontinue potong rondbar
  4. Kontinue repair FWP#3
  5. Lubrication bering CWP pump
  6. Daily maintenance & repair

Elektrik

  1. Chek inverter robot pasir(fkhu)
  2. continue instalasi lighting workshop
  3. Chek kabel out Cctv steam drum#2 ke ccr
  4. daily maintenance

SPB
Nihil

LAPORAN PROGRESS PEKERJAAN COOLING TOWER
Kanis, 27 Juli 2023
Pekerjaan per hari Rabu, 26 Juli 2023
Customer PLTU Baturaja – Sumatra Selatan
Objek Pekerjaan tahap 1. Cooling Tower Unit No 3

Scope Of Work
Mobilisasi dan demobilisasi Alat alat kerja (100%)
Mobilisasi on site accomodasi power (97%)
Performace Tools dam Welding test (100%)
Pembongkaran rangka besi U 2 batang catwalk (100%)
Fabrikasi dan cat dasar rangka besi U 2 batang catwalk (100%)
Pemasangan rangka besi U 2 buah batang catwalk (100%)
Finishing cat rangka besi U 2 buah batang catwalk (100%)
Pembongkaran rangka catwalk, 12 rangka dari 12 rangka, (100%)
Fabrikasi rangka catwalk 12 rangka dari 12 buah rangka, (100%)
Pengecatan dasar rangka catwalk 12 rangka (100%)
Pemasangan rangka catwalk 12 rangka (100%)
Finishing cat rangka catwalk 12 buah rangka, (0%)
Pembongkaran ralling pagar catwalk (100%)
Fabrikasi ralling pagar catwalk (50%)
Pengecatan dasar ralling pagar catwalk (50%)
Pemasangan ralling pagar catwalk (50%)
Finishing cat ralling pagar catwalk (0%)
Fabrikasi ralling pagar (100%)
Pembongkaran ralling pagar luar (100%)
Pemasangan ralling pagar luar (100%)
Pengecatan dasar ralling pagar luar (100%)
Finishing cat ralling pagar (0%)
Pengecatan dasar lantai bordes 70 lembar dari estimate 70 lembar (100%)
Pembongkaran lantai bordes 70 lembar dari estimate 70 lembar (100%)
Rekondisi dan pengecatan dasar rangka lantai bordes (85%)
Setting bordes 45 lembar lantai bordes estimate 70 lembar (60%)
Pengelasan lantai bordes estimate 70 lembar (10%)
Finishing cat lantai bordes (0%)
Pembongkaran tiang pipa (3mtr) breeching horizontal 1,5” 2 batang (100%)
Fabrikasi dan cat dasar tiang pipa (3mtr) breeching horizontal 1,5” 12 batang (100%)
Pemasangan tiang pipa breeching (3mtr) horizontal 1,5” 12 batang (100%)
Finishing cat tiang pipa breeching (3mtr) horizontal 1,5” 12 batang dari 12 batang (75%)
Pembongkaran tiang pipa (3,5mtr) breeching horizontal 1,5” 12 batang (100%)
Fabrikasi dan cat dasar tiang pipa (3,5mtr) breeching horizontal 1,5” 12 btang (100%)
Pemasangan tiang pipa breeching (3,5mtr) horizontal 1,5” 12 batang (100%)
Finishing cat tiang pipa breeching (3,5mtr) horizontal 1,5” 12 batang (100%)
Pembongkaran tiang pipa (3,5mtr) breeching vertikal 3” 4 batang (100%)
Fabrikasi dan cat dasar tiang pipa (3,5mtr) breeching vertikal 3” 4 batang (100%)
Pemasangan tiang pipa (3,5mtr) breeching vertikal 3” 4 batang (100%)
Finishing cat dasar tiang pipa (3,5mtr) breeching vertikal 3” 4 batang (100%)
Pembongkaran tiang pipa breeching (6mtr) diagonal 1,5” 12 batang (100%)
Pemasangan tiang pipa bries (6mtr) diagonal 1,5” 12 batang (100%)
Pengecatan dasar tiang pipa breeching (6mtr) diagonal 1,5” 12 batang (100%)
Finishing cat tiang pipa breeching (6mtr) diagonal 1,5” 12 batang (75%)
Pengangkatan drift eliminator keluar (100%)
Rekondisi drift eliminator (100%)
Pemasangan drift eliminator (0%)
Pembersihan karat pipa penyangga utama dan lantai bordes area kerja
Actual Progress Pekerjaan per hari Rabu, 26 Juli 2023, 82%

Pekerjaan hari Rabu, 26 Juli 2023
• Pembongkaran lantai bordes lanjutan
• Pemasangan ralling pagar lanjutan
• Pengecatan dasar ralling pagar lanjutan
• Seting dan pemasangan bordes lanjutan
• Perbaikan rangka bordes dan finishing cat rangka bordes lanjutan
• Pemasangan ralling catwalk lanjutan
• Pembersihan area kerja dari debu dan serpihan besi dan karat bordes

Rencana Pekerjaan hari Kamis, 27 Juli 2023
• Pembongkaran dan perapihan lantai bordes lanjutan
• Setting dan pemasangan lantai bordes lanjutan
• Pemasangan ralling pagar lanjutan
• Pengecatan rangka grill catwalk lanjutan
• Pemasangan ralling catwalk lanjutan
• Perbaikan rangka bordes dan finishing rangka bordes lanjutan
• Setting, pemasangan dan pengelasan lantai dordes lanjutan
• Pengecatan pipa-pipa breeching dan dudukan drift lanjutan
• Pembersihan area kerja dari debu dan serpihan besi dan karat bordes

Leave a Reply