Kondisi Pembangkit PLTM Lahat 7 Agustus 2023
Kondisi Operasi Mesin
Turbine 1 = ON (0-24)
Turbine 2 = ON (0-24)
Turbine 3 = ON (0-23)
SPB
Nihil
Maintenance
Perbaikan bucket exca 320D







Monitoring All Power Plant Manggala
Kondisi Operasi Mesin
Turbine 1 = ON (0-24)
Turbine 2 = ON (0-24)
Turbine 3 = ON (0-23)
SPB
Nihil
Maintenance
Perbaikan bucket exca 320D