Kondisi Pembangkit PLTU Baturaja 8 Agustus 2023

Kondisi Operasi Mesin
STG 1 = ON (0-24)
STG 2 = ON (0-24)

Maintenance
Mekanik

  1. Continue instal drumb pully belt#1 B
  2. Continue instal FWP#3
  3. Repair kebocoran jalur Ashilo
  4. Continue pabrikasi portal baru
  5. Daily maintenance dan repair
  6. MCU hari kedua

Elektrik

  1. jadwal MCU
  2. support pengawasan pemasangan lampu dcs2
  3. Penggantian motor wjp turbin 1
  4. daily dan maintenance

SPB
Nihil

repair variable speed fluid coupling feed water pump #3

Repair drumb pully belt #2 Finish yang akan di instal di belt conveyor #1B

Drumb pully X belt conveyor #2 selesai di instal di Belt conveyor #1 B

Muhammad Yusufi

Recent Posts

Kondisi Pembangkit PLTM Cibuni 22 Januari 2024

Kondisi Pembangkit PLTM Cibuni 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0-24)…

2 years ago

Kondisi Pembangkit PLTM Endikat 22 Januari 2024

Kondisi Pembangkit PLTM Endikat 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTM Lahat 22 Januari 2024

Kondisi Pembangkit PLTM Lahat 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTU Baturaja 22 Januari 2024

Kondisi Pembangkit PLTU Baturaja 22 Januari 2024 Kondisi Operasi Mesin STG 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTGU MUSI II 22 Januari 2024

Kondisi Pembangkit PLTGU MUSI II 22 Januari 2024 Kondisi Operasi Mesin GTG 1 = ON…

2 years ago

Kondisi Pembangkit PLTM Cibuni 21 Januari 2024

Kondisi Pembangkit PLTM Cibuni 21 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0-24)…

2 years ago