Kondisi Pembangkit PLTU Baturaja 9 Agustus 2023
Kondisi Operasi Mesin
STG 1 = ON (0-24)
STG 2 = ON (0-24)
Maintenance
Mekanik
- Continue pabrikasi portal baru
- Lubrication Auxiliary Boiler & turbine 1&2
- Penggantian bering roller screen #B bagian belakang
- Pengisian oli fluid coupling FWP#3
- Pengecekan glend packing front & back pompa FWP#3
- Fabrikasi Exhaust fan workshop baru
- Daily maintenance & repair
Elektrik
- Support pemasangan lighting Dcs 2
- pemasangan impeler Wjt turbin 1
- penambahan power blower wc office
- continue test alat flow ultrasonic
- daily maintenance
- pabrikasi kabel tray kompressor baru
SPB
Nihil