Kondisi Pembangkit PLTU Baturaja 25 Agustus 2023

Kondisi Operasi Mesin
STG 1 = ON (0-24)
STG 2 = ON (0-24)

Maintenance
Mekanik

1.Continous repair cooling fan#2
2.Inspeksi boiler auxiliary
3.Continous fabrikasi CWR
4.Prepare install pipeline drain mini silo

  • install scaffolding
  • moving pipa ss 8″
    5.Leak repair line transfer ash silo
    6.Lubricating weighing equipment
  • greasing pillow block bearing
  • oiling return & carry Roller

Elektrik

1.Chek dan perbaikan system auto pompa solar CCR
2.Chek instalasi mess kibang
3.continue greasing motor auxiliary
4.perbaikan Cctv level drum #1
5.Daily maintenance

SPB
Nihil

Muhammad Yusufi

Recent Posts

Kondisi Pembangkit PLTM Cibuni 22 Januari 2024

Kondisi Pembangkit PLTM Cibuni 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0-24)…

2 years ago

Kondisi Pembangkit PLTM Endikat 22 Januari 2024

Kondisi Pembangkit PLTM Endikat 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTM Lahat 22 Januari 2024

Kondisi Pembangkit PLTM Lahat 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTU Baturaja 22 Januari 2024

Kondisi Pembangkit PLTU Baturaja 22 Januari 2024 Kondisi Operasi Mesin STG 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTGU MUSI II 22 Januari 2024

Kondisi Pembangkit PLTGU MUSI II 22 Januari 2024 Kondisi Operasi Mesin GTG 1 = ON…

2 years ago

Kondisi Pembangkit PLTM Cibuni 21 Januari 2024

Kondisi Pembangkit PLTM Cibuni 21 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0-24)…

2 years ago