Kondisi Pembangkit PLTU Baturaja 30 Agustus 2023

Kondisi Operasi Mesin
STG 1 = ON (0-24)
STG 2 = ON (0-24)

Maintenance
Mekanik

  1. Lubricating pillow block bearing Ring Hammer 1a dan 1b
  2. Repair gear box rapping ESP Bin #2 dan #3
  3. Repair kebocoran line transfer ash silo
  4. Repair spare block bearing roller screen
  5. Moving alat kerja ke workshop baru
  6. Continue modifikasi pipa pompa ponton

Elektrik

  1. perbaikan lighting crusher area
  2. conection power kontrol air dryer kompressor baru
  3. relokasi motor eks mixer ashsilo
  4. perbaikan panel lighting ashsilo
  5. daily maintenance

SPB
Nihil