Kondisi Pembangkit PLTM Cibuni 2 September 2023
Kondisi Pembangkit PLTM Cibuni 2 September 2023
Kondisi Operasi Mesin
Turbine 1 = OFF (0-24)
Turbine 2 = ON (0-24)
Monitoring All Power Plant Manggala
Kondisi Pembangkit PLTM Cibuni 2 September 2023
Kondisi Operasi Mesin
Turbine 1 = OFF (0-24)
Turbine 2 = ON (0-24)
Kondisi Pembangkit PLTM Endikat 2 September 2023
Kondisi Operasi Mesin
Turbine 1 = ON (0-24)
Turbine 2 = OFF
Turbine 3 = ON (0-24)
Kondisi Pembangkit PLTM Lahat 2 September 2023
Kondisi Operasi Mesin
Turbine 1 = ON (0-24)
Turbine 2 = ON (0-24)
Turbine 3 = OFF
Kondisi Pembangkit PLTU Baturaja 2 September 2023
Kondisi Operasi Mesin
STG 1 = ON (0-24)
STG 2 = ON (0-24)
Kondisi Pembangkit PLTGU MUSI II 2 September 2023
Kondisi Operasi Mesin
GTG 1 = ON (8-16)
GTG 2 = ON (0-24)
GTG 3 = ON (0-24)
STG = ON (0-24)