Kondisi Pembangkit PLTU Baturaja 12 September 2023

Kondisi Operasi Mesin
STG 1 = ON (0-24)
STG 2 = ON (0-24)

Maintenance
Mekanik

  1. Repair kebocoran line transfer ash silo
  2. Repair kebocoran ducting weighing #2
  3. Repair V-frame carry roller B/C #2
  4. Repair transfer Valve vessel#3 dan # 4
  5. Lanjut bikin rak spare parts workshop baru
  6. Lanjut moving spare parts dari workshop lama
  7. Inspeksi Drive pulley B/C #2 dan penambahan baut cassing
  8. Lanjut pekerjaan pompa ponton

Elektrik

  1. Penggantian silica gel transformer
  2. pelumasan motor cooling tower, cwp dan auxiliary boiler
  3. continue daily transformer
  4. Penggantian angker gerinda elektrik
  5. support pengamanan kabel cctv team umum perbaikan dinding dcs 1
Muhammad Yusufi

Recent Posts

Kondisi Pembangkit PLTM Cibuni 22 Januari 2024

Kondisi Pembangkit PLTM Cibuni 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0-24)…

2 years ago

Kondisi Pembangkit PLTM Endikat 22 Januari 2024

Kondisi Pembangkit PLTM Endikat 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTM Lahat 22 Januari 2024

Kondisi Pembangkit PLTM Lahat 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTU Baturaja 22 Januari 2024

Kondisi Pembangkit PLTU Baturaja 22 Januari 2024 Kondisi Operasi Mesin STG 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTGU MUSI II 22 Januari 2024

Kondisi Pembangkit PLTGU MUSI II 22 Januari 2024 Kondisi Operasi Mesin GTG 1 = ON…

2 years ago

Kondisi Pembangkit PLTM Cibuni 21 Januari 2024

Kondisi Pembangkit PLTM Cibuni 21 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0-24)…

2 years ago