Categories: PLTU BATURAJA

Kondisi Pembangkit PLTU Baturaja 18 September 2023

Kondisi Operasi Mesin
STG 1 = ON (16-24)
STG 2 = ON (0 – 24 )

Maintenance
Mekanik

  1. Cleaning area workshop
  2. Lanjut pekerjaan pompa ponton
  3. Greasing pillow block bearing ring hammer & Greasing all parts B/C weighing
  4. Fabrikasi tambahan rack spare parts workshop
  5. Repair kebocoran line transfer ash silo
  6. support start up boiler #1
    Cleaning burner
    Setting B/C Weighing #1 after repair.

Electric

  1. Support lighting dan chek boiler1
  2. Support optimalisasi hoist dcs1
  3. Support start up boiler#1
  4. Daily maintenance

Cleaning dan pengecekan nozle purnace On progress

Cleaning burner ignition #A dan B

Muhammad Yusufi

Recent Posts

Kondisi Pembangkit PLTM Cibuni 22 Januari 2024

Kondisi Pembangkit PLTM Cibuni 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0-24)…

2 years ago

Kondisi Pembangkit PLTM Endikat 22 Januari 2024

Kondisi Pembangkit PLTM Endikat 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTM Lahat 22 Januari 2024

Kondisi Pembangkit PLTM Lahat 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTU Baturaja 22 Januari 2024

Kondisi Pembangkit PLTU Baturaja 22 Januari 2024 Kondisi Operasi Mesin STG 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTGU MUSI II 22 Januari 2024

Kondisi Pembangkit PLTGU MUSI II 22 Januari 2024 Kondisi Operasi Mesin GTG 1 = ON…

2 years ago

Kondisi Pembangkit PLTM Cibuni 21 Januari 2024

Kondisi Pembangkit PLTM Cibuni 21 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0-24)…

2 years ago