Kondisi Pembangkit PLTM Cibuni 30 September 2023
Kondisi Pembangkit PLTM Cibuni 30 September 2023
Kondisi Operasi Mesin
Turbine 1 = ON (0-24)
Turbine 2 = OFF (0-24)
Monitoring All Power Plant Manggala
Kondisi Pembangkit PLTM Cibuni 30 September 2023
Kondisi Operasi Mesin
Turbine 1 = ON (0-24)
Turbine 2 = OFF (0-24)
Kondisi Pembangkit PLTM Endikat 30 September 2023
Kondisi Operasi Mesin
Turbine 1 = On ( O-6)
Turbine 2 = On ( O-18 )
Turbine 3 = On ( O-24 )
Kondisi Pembangkit PLTM Lahat 30 September 2023
Kondisi Operasi Mesin
Turbine 1 = On ( O – 24)
Turbine 2 = Off
Turbine 3 = On ( O – 24)
Kondisi Pembangkit PLTU Baturaja 30 September 2023
Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON (0 – 24 )
Kondisi Pembangkit PLTGU MUSI II 30 September 2023
Kondisi Operasi Mesin
GTG 1 = ON (0-24)
GTG 2 = ON (8-16)
GTG 3 = ON (0-24)
STG = ON (0-24)
Kondisi Pembangkit PLTM Cibuni 29 September 2023
Kondisi Operasi Mesin
Turbine 1 = OFF (0-24)
Turbine 2 = OFF (0-24)
Kondisi Pembangkit PLTM Endikat 29 September 2023
Kondisi Operasi Mesin
Turbine 1 = On ( O-4)
Turbine 2 = On ( O-19 )
Turbine 3 = On ( O-19 )
Kondisi Pembangkit PLTM Lahat 29 September 2023
Kondisi Operasi Mesin
Turbine 1 = On ( O – 24)
Turbine 2 = Off
Turbine 3 = On ( O – 24)
Kondisi Pembangkit PLTU Baturaja 29 September 2023
Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON (0 – 24 )
Kondisi Pembangkit PLTGU MUSI II 29 September 2023
Kondisi Operasi Mesin
GTG 1 = ON (0-24)
GTG 2 = OFF
GTG 3 = ON (0-24)
STG = ON (0-24)