Categories: PLTU BATURAJA

Kondisi Pembangkit PLTU Baturaja 3 Oktober 2023

Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON (0 – 24 )

Maintenance
Mekanik

  1. Cleaning area work shop
  2. 2.Inspeksi ESP
  3. 3.Repair kebocoran line transfer ash silo
  4. 4.Prepaired Install Long Bow Ceramic Liner
    -Jointing Ceramic Liner Pipe to Long Bow
    -Install guntry Chain block
  5. Continous Fabrikasi Rack Spare parts Logistic
  6. Penggantian Pompa Ponton #1
  7. Suport team subkon PT Lumbung finishing installation dan test pressure pipa kompresor sulair#2

Electrik

  1. support team vendor chek kondisi genset black start
  2. penggantian monitor level drum
  3. chek komunikasi penyulang Ccr
  4. continue daily maintenance
  5. perawatan light pump house

Pengecekan dan inspection untuk optimalisasi genset blacsktart dan transporter PLTU oleh team vendor di dampingi team elektrik pak Edi R dan HSE K3 listrik Bapak azis

Muhammad Yusufi

Recent Posts

Kondisi Pembangkit PLTM Cibuni 22 Januari 2024

Kondisi Pembangkit PLTM Cibuni 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0-24)…

2 years ago

Kondisi Pembangkit PLTM Endikat 22 Januari 2024

Kondisi Pembangkit PLTM Endikat 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTM Lahat 22 Januari 2024

Kondisi Pembangkit PLTM Lahat 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTU Baturaja 22 Januari 2024

Kondisi Pembangkit PLTU Baturaja 22 Januari 2024 Kondisi Operasi Mesin STG 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTGU MUSI II 22 Januari 2024

Kondisi Pembangkit PLTGU MUSI II 22 Januari 2024 Kondisi Operasi Mesin GTG 1 = ON…

2 years ago

Kondisi Pembangkit PLTM Cibuni 21 Januari 2024

Kondisi Pembangkit PLTM Cibuni 21 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0-24)…

2 years ago