Kondisi Pembangkit PLTU Baturaja 4 Oktober 2023
Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON (0 – 24 )
Maintenance
Mekanik
- Cleaning area work shop
- Inspeksi ESP
- Repair kebocoran line transfer ash silo
- Prepaired Install Long Bow Ceramic Liner
-Jointing Ceramic Liner Pipe to Long Bow
-Install guntry Chain block - Continous Fabrikasi Rack Spare parts Logistic
- PM WTP
-Rekondisi pompa ponton ( ganti bearing )
-Perawatan SC & SW Pumps - PM.Boiler
Inspeksi All H/E
Tambah Oli IDF - PM Genset Black Start
-Tighten oil filter
Elektrik
- connect kabel power kompressor sullair
- perbaikan lighting elv 14.5 Mpb
- Penarikan kabel ethernet penyulang CCR
- daily maintenance
SPB
Nihil
Prepare untuk penggantian longbow pipa transfer Ashilo manufacture taychun




Prepare power kompresor#2 sulair untuk commissioning