Kondisi Pembangkit PLTM Endikat 7 Oktober 2023
Kondisi Operasi Mesin
Turbine 1 = Off
Turbine 2 = On ( O-19 )
Turbine 3 = On ( O-23 )
SPB
Nihil
Maintenance
Lanjut Penimbunan sisi kiri bak penenang HP
Monitoring All Power Plant Manggala
Kondisi Operasi Mesin
Turbine 1 = Off
Turbine 2 = On ( O-19 )
Turbine 3 = On ( O-23 )
SPB
Nihil
Maintenance
Lanjut Penimbunan sisi kiri bak penenang HP