Kondisi Pembangkit PLTU Baturaja 6 Oktober 2023

Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON (0 – 24 )

Maintenance
Mekanik

  1. Cleaning area work shop
  2. Inspeksi All Weighing conveyor
  3. Repair kebocoran line transfer ash silo
  4. Prepaired Install Long Bow Ceramic Liner
    -Jointing Ceramic Liner Pipe to Long Bow
    -jointing flange
  5. PM WTP
    Repair SC Pumps #1
  6. Inspeksi Crusher
    pengencangan mur angkur tambahan
  7. Repair Drive Pulley Conveyor
    Dismantling planetary gear

Elektrik

  1. Pengecekan motor pompa SC #1 Abnormal
  2. Cek meger laminasi motor SC#1
  3. Penambahan inverter di pompa SC#3 yang baru

Abnormal pompa SC #1 progres repair, SC#3 On pakai inverter spare

Muhammad Yusufi

Recent Posts

Kondisi Pembangkit PLTM Cibuni 22 Januari 2024

Kondisi Pembangkit PLTM Cibuni 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0-24)…

2 years ago

Kondisi Pembangkit PLTM Endikat 22 Januari 2024

Kondisi Pembangkit PLTM Endikat 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTM Lahat 22 Januari 2024

Kondisi Pembangkit PLTM Lahat 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTU Baturaja 22 Januari 2024

Kondisi Pembangkit PLTU Baturaja 22 Januari 2024 Kondisi Operasi Mesin STG 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTGU MUSI II 22 Januari 2024

Kondisi Pembangkit PLTGU MUSI II 22 Januari 2024 Kondisi Operasi Mesin GTG 1 = ON…

2 years ago

Kondisi Pembangkit PLTM Cibuni 21 Januari 2024

Kondisi Pembangkit PLTM Cibuni 21 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0-24)…

2 years ago