Kondisi Pembangkit PLTU Baturaja 10 Oktober 2023

Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON (0 – 24 )

Maintenance
Mekanik

  1. Cleaning area work shop
  2. Inspeksi All Weighing conveyor
  3. start up compressor SULLAIR #1
  4. Install ceramic long bow
    Tie in
  5. Repair kebocoran line transfer ash silo.
  6. Rekondisi Pompa S.C # 1
  7. Perawatan pompa auxiliary WTP

Elektrik

  1. Commisioning kompresor#1 sulair bersama team maintenance
  2. Support pengecekan power kompresor saat running loading and unloading
  3. Support team mekanik repair pompa SC#1
  4. Connect power SC and trail running

SPB
Nihil

Commisioning kompresor #1 sulair kompresor#2 Off prepare maintenance 8000 jam
Running hour load kompresor#2 sampai hari ini 7431 jam

Pompa SC#1 ready & running setelah selesai repair

Instal longbow Ashilo taychun manufacture 2 line jalur velsel#3&6 finish 🙏🏻

Tagging penomoran kompresor baru sudah di pasang team QC