Kondisi Pembangkit PLTM Endikat 23 Oktober 2023
Kondisi Operasi Mesin
Turbine 1 = ON (0-23)
Turbine 2 = ON (0-8)
Turbine 3 = ON (0-5)
SPB
Nihil
Maintenance
- penimbunan Di area HP
- Pembanguan sidedicht sta 500
Monitoring All Power Plant Manggala
Kondisi Operasi Mesin
Turbine 1 = ON (0-23)
Turbine 2 = ON (0-8)
Turbine 3 = ON (0-5)
SPB
Nihil
Maintenance