Kondisi Pembangkit PLTM Lahat 27 Oktober 2023
Kondisi Operasi Mesin
Turbine 1 = ON (0 – 2)
Turbine 2 = ON (0 – 24)
Turbine 3 = Off (0 – 22)
SPB
Nihil
Maintenance
pengecekkan vibrasi unit 1,2 dan 3
Monitoring All Power Plant Manggala
Kondisi Operasi Mesin
Turbine 1 = ON (0 – 2)
Turbine 2 = ON (0 – 24)
Turbine 3 = Off (0 – 22)
SPB
Nihil
Maintenance
pengecekkan vibrasi unit 1,2 dan 3