Categories: PLTU BATURAJA

Kondisi Pembangkit PLTU Baturaja 30 Oktober 2023

Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON (0 – 24 )

Maintenance
Mekanik

  1. Cleaning area work shop
  2. Inspeksi All Weighing conveyor
    Lubricating All rotating parts
  3. Inspeksi kompresor SULLAIR
  4. Ganti elbow doubling plate area akses boiler make up
  5. Repair kebocoran line transfer Ash Silo
  6. Pekerjaan Ponton
    1. Fabrikasi suction pipe pompa ponton nomor 1&2
    2. Pengecatan ponton dengan plintkote
  7. Inspeksi ESP
    Lubricating all Gearbox Rapping

Elektrik

  1. .perawatan panel lighting Ash silo dan DCS
  2. Perbaikan lighting ash silo
  3. perawatan panel Plc demin dan elv 26
  4. Perbaikan dan perawatan grounding
  5. Daily maintenance

SPB
Nihil

penggantian sensor temp combistion boiler 1.

Perawatan panel Plc demin wtp

Perawatan panel lighting DCS

Muhammad Yusufi

Recent Posts

Kondisi Pembangkit PLTM Cibuni 22 Januari 2024

Kondisi Pembangkit PLTM Cibuni 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0-24)…

2 years ago

Kondisi Pembangkit PLTM Endikat 22 Januari 2024

Kondisi Pembangkit PLTM Endikat 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTM Lahat 22 Januari 2024

Kondisi Pembangkit PLTM Lahat 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTU Baturaja 22 Januari 2024

Kondisi Pembangkit PLTU Baturaja 22 Januari 2024 Kondisi Operasi Mesin STG 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTGU MUSI II 22 Januari 2024

Kondisi Pembangkit PLTGU MUSI II 22 Januari 2024 Kondisi Operasi Mesin GTG 1 = ON…

2 years ago

Kondisi Pembangkit PLTM Cibuni 21 Januari 2024

Kondisi Pembangkit PLTM Cibuni 21 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0-24)…

2 years ago