Kondisi Pembangkit PLTM Endikat 8 November 2023
Kondisi Operasi Mesin
Turbine 1 = ON (0-24)
Turbine 2 = ON (0-19)
Turbine 3 = ON (0-5)
SPB
Nihil
Maintenance
ROW section 1 s/3
Monitoring All Power Plant Manggala
Kondisi Operasi Mesin
Turbine 1 = ON (0-24)
Turbine 2 = ON (0-19)
Turbine 3 = ON (0-5)
SPB
Nihil
Maintenance
ROW section 1 s/3