Kondisi Pembangkit PLTU Baturaja 10 November 2023

Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON (0 – 24 )

Maintenance
Mekanik

  1. Cleaning area workshop
  2. Inspeksi All Weighing conveyor
  3. Inspeksi kompresor SULLAIR
  4. Repair kompresor FEIHE NO.#2 ( Indikasi bearing screw jaming )
    Dismantling All parts & Cleaning
  5. Fabrikasi doubling plate elbow Ash silo (Elbow Manganese Steel)
  6. P/M Boiler & Turbine
    Perawatan dan pengecekan H/E all
  7. P/M WTP
    penggantian frame dan plate bordes lantai wtp
    pengawalan penggalian siring rel pjka
  8. Repair bocor line transfer Ash silo.

Elektrik

  1. Perbaikan & Pabrikasi Modul PM Ex.Generator.
  2. Perawatan Panel Auxiliary Crusher & Panel Roller Screen 1b
  3. Continue pengawasan penggalian area rel
  4. Continue perbaikan motor Cwp
  5. Perbaikan grounding demin
  6. Daily maintenance

SPB
Nihil

Melakukan perawatan pompa SC dan SW

Penggantian kompresor purifire #1

pemasangan scund dan insulating kabel

Muhammad Yusufi

Recent Posts

Kondisi Pembangkit PLTM Cibuni 22 Januari 2024

Kondisi Pembangkit PLTM Cibuni 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0-24)…

2 years ago

Kondisi Pembangkit PLTM Endikat 22 Januari 2024

Kondisi Pembangkit PLTM Endikat 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTM Lahat 22 Januari 2024

Kondisi Pembangkit PLTM Lahat 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTU Baturaja 22 Januari 2024

Kondisi Pembangkit PLTU Baturaja 22 Januari 2024 Kondisi Operasi Mesin STG 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTGU MUSI II 22 Januari 2024

Kondisi Pembangkit PLTGU MUSI II 22 Januari 2024 Kondisi Operasi Mesin GTG 1 = ON…

2 years ago

Kondisi Pembangkit PLTM Cibuni 21 Januari 2024

Kondisi Pembangkit PLTM Cibuni 21 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0-24)…

2 years ago