Kondisi Pembangkit PLTU Baturaja 13 November 2023

Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON (0 – 24 )

Maintenance
Mekanik

  1. Cleaning area workshop
  2. Inspeksi All Weighing conveyor
  3. Inspeksi kompresor SULLAIR
  4. Continous Fabrikasi doubling plate elbow Ash silo (Elbow Manganese Steel)
    Concrete Filling
  5. Continue fabrikasi Knalpot W/L
  6. Repair ESP Vessel #1
    Ganti gasket F/V
  7. Melakukan perbaikan pompa ammonia no. 1
  8. Melakukan Perbaikan pompa biocide.
  9. Melakukan penggantian drain valve pompa koagulan
  10. Melakukan perawatan dan penggantian HE pada SAF #2 Boiler#2

Elektrik

  1. Daily maintenance transformer
  2. Change probe sensor conductivity Boiler make-up / Demin
  3. Repair control panel Botol #5
  4. Continue repair terminasi kabel power motor CWP pump#1

Abnormal heat Exchanger bloking Primary airfan #2 boiler#2 bloking, menyebabkan variable speed coupling overheat, Alhamdulillah penggantian HE baru tidak sampai stop unit dan running kembali