Kondisi Pembangkit PLTU Baturaja 24 November 2023

Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON (0 – 24 )

Maintenance
Mekanik

  1. Cleaning area workshop
  2. Inspeksi All Weighing conveyor
  3. Inspeksi kompresor SULLAIR
  4. P/M TURBIN
    Melakukan Fabrikasi maintenance dact diatas water jet tank pump turbine #1
  5. P/M IDF
    Melakukan pengecekan dan penambahan oil block bearing IDF #2 Dan #4
  6. P/M WTP
    -Melakukan perakitan foot valve ex ponton
  7. Repair ESP
    Gasketing bottom screen Vessel #5
    Gasketing F/V Vessel #2
  8. Repair kebocoran line Transfer Ash silo
  9. Fabrikasi Elbow doubling plate untuk line #3 & # 6 area tangga ESP.

Electrik

  1. Chek accu genset 75kw
  2. Chek dan perawatan penangkal petir chimney
  3. test dan perbaikan sensor level botol 5 Esp
  4. Daily maintenance

SPB
Nihil

Leave a Reply

Your email address will not be published. Required fields are marked *