Kondisi Pembangkit PLTGU MUSI II 27 November 2023
Kondisi Pembangkit PLTGU MUSI II 27 November 2023
Kondisi Operasi Mesin
GTG 1 = OFF (0-24)
GTG 2 = ON (0-24)
GTG 3 = ON (0-24)
STG = ON (0-24)
Monitoring All Power Plant Manggala
Kondisi Pembangkit PLTGU MUSI II 27 November 2023
Kondisi Operasi Mesin
GTG 1 = OFF (0-24)
GTG 2 = ON (0-24)
GTG 3 = ON (0-24)
STG = ON (0-24)
Kondisi Pembangkit PLTM Cibuni 26 November 2023
Kondisi Operasi Mesin
Turbine 1 = OFF (0-24)
Turbine 2 = ON (22-24)
Kondisi Pembangkit PLTM Endikat 26 November 2023
Kondisi Operasi Mesin
Turbine 1 = ON (0 – 23)
Turbine 2 = ON (0 – 17)
Turbine 3 = ON (0 – 24)
Kondisi Pembangkit PLTM Lahat 26 November 2023
Kondisi Operasi Mesin
Turbine 1 = ON (0 – 24)
Turbine 2 = ON (0 – 24)
Turbine 3 = ON (0 – 17)
Kondisi Pembangkit PLTU Baturaja 25 November 2023
Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON (0 – 24 )
Kondisi Pembangkit PLTGU MUSI II 26 November 2023
Kondisi Operasi Mesin
GTG 1 = OFF (0-24)
GTG 2 = ON (0-24)
GTG 3 = ON (0-24)
STG = ON (0-24)
Kondisi Pembangkit PLTM Cibuni 25 November 2023
Kondisi Operasi Mesin
Turbine 1 = OFF (0-24)
Turbine 2 = ON (0-24)
Kondisi Pembangkit PLTM Endikat 25 November 2023
Kondisi Operasi Mesin
Turbine 1 = ON (0 – 23)
Turbine 2 = ON (0 – 22)
Turbine 3 = ON (0 – 17)
Kondisi Pembangkit PLTM Lahat 25 November 2023
Kondisi Operasi Mesin
Turbine 1 = ON (0 – 24)
Turbine 2 = ON (0 – 24)
Turbine 3 = ON (0 – 15)
Kondisi Pembangkit PLTU Baturaja 25 November 2023
Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON (0 – 24 )