Kondisi Pembangkit PLTM Cibuni 28 November 2023
Kondisi Pembangkit PLTM Cibuni 28 November 2023
Kondisi Operasi Mesin
Turbine 1 = ON (0-24)
Turbine 2 = ON (0-24)
Monitoring All Power Plant Manggala
Kondisi Pembangkit PLTM Cibuni 28 November 2023
Kondisi Operasi Mesin
Turbine 1 = ON (0-24)
Turbine 2 = ON (0-24)
Kondisi Pembangkit PLTM Endikat 28 November 2023
Kondisi Operasi Mesin
Turbine 1 = ON (0 – 24)
Turbine 2 = ON (0 – 23)
Turbine 3 = ON (0 – 24)
Kondisi Pembangkit PLTM Lahat 28 November 2023
Kondisi Operasi Mesin
Turbine 1 = ON (0 – 24)
Turbine 2 = ON (0 – 24)
Turbine 3 = ON (0 – 23)
Kondisi Pembangkit PLTU Baturaja 28 November 2023
Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON (0 – 24 )
Kondisi Pembangkit PLTGU MUSI II 28 November 2023
Kondisi Operasi Mesin
GTG 1 = ON (9-24)
GTG 2 = ON (0-24)
GTG 3 = OFF (0-16)
STG = ON (0-24)
Kondisi Pembangkit PLTM Cibuni 27 November 2023
Kondisi Operasi Mesin
Turbine 1 = ON (0-24)
Turbine 2 = ON (0-24)
Kondisi Pembangkit PLTM Endikat 27 November 2023
Kondisi Operasi Mesin
Turbine 1 = ON (0 – 24)
Turbine 2 = ON (0 – 22)
Turbine 3 = ON (0 – 22)
Kondisi Pembangkit PLTM Lahat 27 November 2023
Kondisi Operasi Mesin
Turbine 1 = ON (0 – 22)
Turbine 2 = ON (0 – 23)
Turbine 3 = ON (0 – 23)
Kondisi Pembangkit PLTU Baturaja 27 November 2023
Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON (0 – 24 )