Kondisi Pembangkit PLTU Baturaja 29 November 2023

Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON (0 – 24 )

Maintenance
Mekanik

  1. Cleaning area workshop
  2. Inspeksi All Weighing conveyor
  3. Inspeksi kompresor SULLAIR
  4. Repair kebocoran line Transfer Ash silo.
    Area ESP
  5. Install pipa ceramic liner line transfer ash silo area top main silo
  6. Inspeksi ESP Vessel # 3
  7. Repair screen R/H
  8. Penanggulangan kebocoran pada H/E fwp
  9. Repair H/E spare
  10. Fabrikasi pipa return SC ke reserpoar

Electrik

  1. Schedule safety talk
  2. Perawatan Panel Area Waterpond dan Cwp & Check Ats change Line Control
  3. continue perawatan ac Mpb dan distribusi room
  4. Merapikan power di area fwp eks mekanik
  5. Persiapan power dan lighting oh
  6. Daily maintenance

SPB
Nihil