Kondisi Pembangkit PLTU Baturaja 11 Desember 2023
Kondisi Operasi Mesin
STG 1 = ON (16.52 – 0)
STG 2 = ON (0 – 22 )
Maintenance
Mekanik
I. Daily Jobs
1. Inspeksi kompresor SULLAIR
2. Inspeksi Weighing
II. Over Haule
- Finishing Reposisi pipa drain manual vessel #2 & vessel #3
Penambahan pipa buang
reinstall cover - Cleaning scrap ex OH ESP #1
- Re insulating All item ex OH
Flexible joint exhaust ducting boiler #1 Elv.0
Valve drain flash tank DN 50 boiler#1 Elv.7
Valve FWP Elv.7 - Repair Top hoist ESP #2
Seling kusut
Elektrik
- Switching kembali trafo#1masih ada rembesan dalam oli
- Support team mekanik
• SPB
Nihil
Progress OH unit#1 PLTU Baturaja, 11 Desember 2023
Boiler #1
- Stop Boiler #1, 100%
- Cooling Boiler, ESP, drain debu ESP, 100%
- Cleaning ESP 1 (Drain), 100%
- Perbaikan ESP 1, 100%
- Perbaikan Screen Outlet ESP 1, 100%
- Penggantian dan perbaikan Valve DN20 2 Pcs Elv. 26 dekat Drum Boiler #1, 100%
- Kebocoran pipa drain Collection di Elv.7 Boiler #1, 100%
- Kalibrasi Sensor Boiler #1 & Greasing SAF & PAF, 100%
- Kebocoran pipa jalur pasir Syclone arah SWAS Room Boiler #1, 100%
- Kebocoran Pipa Downcomer dan Valve Collection Elv.0 Boiler #1 , 100%
- Cleaning Air Heater Boiler #1, 100%
- Cleaning Burner Boiler #1, 100%
- Cleaing Nozle Furnace Boiler #1, 100%
- Cleaning Nozle Solar Boiler #1, 100%
- Start Boiler #1, 0%
Turbin#1
- Stop Turbine #1, 100%
- Pengecekan (Perbaikan) Kebocoran Fleksible Joint Oli Governour Turbine #1, 100%
- Pengecekan (Perbaikan) rembesan Oli di MSV Turbine #1, 100%
- Pengecekan (Perbaikan) gasket HPH Turbine #1, 100%
- Pengecekan (penggantian) manual gasket valve bypass Inlet Economizer di Elv. 7 dekat kamar mandi CCR, 100%
- Perbaikan Trafo 20KV, 100%
- Cleaning Oil Cooler 1&2, 100%
- Cleaning Air Cooler Generator, 100%
- Start Turbine #1, 0%
- Perbaikan sand filter 1,2 dan 3 45%
- Perbaikan pondasi Ring Hammer, 30%
Additional work setelah stop unit#1
- Repair kebocoran deck area isolator ESP#1, 100%
- Penggantian Spiral Wond Drain Extraction Turbine 1 Elv. 3,5 100%
- Penggantian gasket Bypass Steam Turbine 1 Elv. 3,5 100%
- Perbaikan transmiter Main Steam Header 2 Boiler 1 100%
- Penggantian Valve Sensor Main Steam Turbine 1 100%
- Penambalan kebocoran pipa Cooler Generator 1 100%
- Perbaikan Dinding Furnice yang rontok 100%
- Cleaning Ducting PAF dan SAF Boiler 1 100%
- Perbaikan Dumper PAF Inlet Air Furnice Boiler 1 sisi Demin 100%
- Repair kebocoran mangkok SteamBlow Boiler 1 100%
- Cleaning Water Filter Turbine 1 100%
- Perbaikan Pin Getpost Turbine 1 sisi Cooling Tower 100%
- Repair kebocoran Gasket Flange main Steam Drum ke Pressure Transmiter Elv.32 Boiler 1 100%
- Pengelasan Joint antara sisi A dan sisi B Air Heater PAF bagian Outlet Elv. 11 Boiler 1 100%
- Perbaikan kebocoran Ducting SAF dekat leher angsa Elv.0 Boiler 1 100%
- Perbaikan Casing Inveler IDFan 2 100%
- Perbaikan Casing Inveler IDFan 1 100%
- Pemindahan jalur drain manual vesel 2 dan 3 ESP 1 100%
Alhamdulillah Unit#1 close
Unit#1 sinkron dengan jaringan jam 16.52