Kondisi Pembangkit PLTU Baturaja 5 Desember 2023

Kondisi Operasi Mesin
STG 1 = OFF
STG 2 = ON (0 – 24 )

Maintenance
Progress OH unit#1 PLTU Baturaja, 05 Desember 2023

Boiler#1

  1. Stop Boiler 1, 100%
  2. Cooling boiler, ESP, drain debu ESP, 100%
  3. Cleaning ESP 1 (Drain), 100%
  4. Perbaikan ESP 1, (On progress )
  5. Perbaikan Screen Outlet ESP 1, (On progress)
  6. Penggantian dan perbaikan Valve DN20 2 Pcs Elv. 26 dekat Drum Boiler #1, 100 %
  7. Kebocoran pipa drain Collection di Elv. 7 Boiler, 0 %
  8. Kalibrasi Sensor Boiler & Greasing SAF dan PAF, 0 %
  9. Kebocoran pipa jalur pasir Syclone arah SWAS Room Boiler #1, 0%
  10. Kebocoran Pipa Downcomer dan Valve Collection Elv. 0 Boiler #1 , 0 %
  11. Cleaning Air Heater Boiler 1, 0%
  12. Cleaning Burner Boiler 1, 0%
  13. Cleaing Nozle Furnace Boiler 1, ( On progress)
  14. Cleaning Nozle Solar Boiler 1, 0%
  15. Start Boiler 1, 0%

Turbin#1

  1. Stop Turbine #1, 100%
  2. Pengecekan (Perbaikan) Kebocoran Fleksible Joint Oli Governour Turbine #1, 0%
  3. Pengecekan (Perbaikan) rembesan Oli di MSV Turbine #1, 0%
  4. Pengecekan (Perbaikan) gasket HPH Turbine #1, 100%
  5. Pengecekan (penggantian) manual gasket valve bypass Inlet Economizer di Elv. 7 dekat kamar mandi CCR, ( On progress)
  6. Perbaikan Trafo 20KV, (on progress
  7. Cleaning Oil Cooler 1&2, (On progress)
  8. Cleaning Air Cooler Generator, (On progress)
  9. Start Turbine #1, 0%

Tanpa padam unit

  1. Cleaning sand filter, (On progress )
  2. Perbaikan pondasi ring hammer, 0 %
    •SPB
    Nihil

Leave a Reply

Your email address will not be published. Required fields are marked *