Kondisi Operasi Mesin
STG 1 = OFF
STG 2 = ON (0 – 24 )
Maintenance
- Repair kebocoran pipa transfer botol#6
- Pengecekan monitor CCR #2 mati mendadak
Progress OH unit#1 PLTU Baturaja, 07 Desember 2023
Boiler#1
- Stop Boiler 1, 100%
- Cooling boiler, ESP, drain debu ESP, 100%
- Cleaning ESP 1 (Drain), 100%
- Perbaikan ESP 1, 50%
- Perbaikan Screen Outlet ESP 1, 100 %
- Penggantian dan perbaikan Valve DN20 2 Pcs Elv. 26 dekat Drum Boiler #1, 100 %
- Kebocoran pipa drain Collection di Elv. 7 Boiler, 100 %
- Kalibrasi Sensor Boiler & Greasing SAF dan PAF, 100 %
- Kebocoran pipa jalur pasir Syclone arah SWAS Room Boiler #1, 100%
- Kebocoran Pipa Downcomer dan Valve Collection Elv.0 Boiler #1 , 100 %
- Cleaning Air Heater Boiler 1, ( On progress)
- Cleaning Burner Boiler 1, 100%
- Cleaing Nozle Furnace Boiler 1, 100 %
- Cleaning Nozle Solar Boiler 1, 0%
- Start Boiler 1, 0%
Turbin#1
- Stop Turbine #1, 100%
- Pengecekan (Perbaikan) Kebocoran Fleksible Joint Oli Governour Turbine #1, 0%
- Pengecekan (Perbaikan) rembesan Oli di MSV Turbine #1, 100%
- Pengecekan (Perbaikan) gasket HPH Turbine #1, 100%
- Pengecekan (penggantian) manual gasket valve bypass Inlet Economizer di Elv. 7 dekat kamar mandi CCR, 100%
- Perbaikan Trafo 20KV, (on progress
- Cleaning Oil Cooler 1&2, (On progress)
- Cleaning Air Cooler Generator, 90 %
- Start Turbine #1, 0%
Tanpa padam unit
- Cleaning sand filter, 50%
- Perbaikan pondasi ring hammer, ( On progress)
Additional work setelah stop unit#1
- Repair kebocoran deck area isolator ESP#1, 50%