Kondisi Pembangkit PLTU Baturaja 9 Desember 2023
Kondisi Operasi Mesin
STG 1 = OFF
STG 2 = ON (0 – 24 )
Maintenance
Mekanik
- Finishing ESP #1
- Reinstall stoper CP yg lepas.
- Perapihan cover plat flexible Joint area elektroda room
- Reinstall rapping yang lepas dan rusak ( ganti baru )
-Cleaning
2. Support Mr.Lee install lock pin Turbine #1
3. Repair Valve venting upper steam drum DN 15 PN 100
- Ganti gasket
4. Repair manual valve DN 80 PN 100 Steam Blow Boiler #1
- Ganti gasket Bonet
5. Repair kebocoran pada casing IDF #1 dan IDF #2
6.Repair sand filter #2 dan #3
7.Melakukan repair kebocoran pada discharge pipe dan penambahan Baut flange suction pipe pompa ponton #1
8.Improvement pembuatan pipa udara untuk backwosh pada sand filter #2
Elektrik
- Suport team mekanik
- Suport team subkon trafo
- SPB
Nihil
Progress OH unit#1 PLTU Baturaja, 09 Desember 2023
Boiler#1
- Stop Boiler 1, 100%
- Cooling boiler, ESP, drain debu ESP, 100%
- Cleaning ESP 1 (Drain), 100%
4.Perbaikan ESP 1, 80 %
5.Perbaikan Screen Outlet ESP 1, 100 %
6.Penggantian dan perbaikan Valve DN20 2 Pcs Elv. 26 dekat Drum Boiler #1, 100 % - Kebocoran pipa drain Collection di Elv. 7 Boiler, 100 %
8.Kalibrasi Sensor Boiler & Greasing SAF dan PAF, 100 %
9.Kebocoran pipa jalur pasir Syclone arah SWAS Room Boiler #1, 100% - Kebocoran Pipa Downcomer dan Valve Collection Elv.0 Boiler #1 , 100 %
- Cleaning Air Heater Boiler 1, 70 %
- Cleaning Burner Boiler 1, 100%
- Cleaing Nozle Furnace Boiler 1, 100 %
- Cleaning Nozle Solar Boiler 1, 100%
- Start Boiler 1, 0%
Turbin#1
- Stop Turbine #1, 100%
- Pengecekan (Perbaikan) Kebocoran Fleksible Joint Oli Governour Turbine #1, 100%
- Pengecekan (Perbaikan) rembesan Oli di MSV Turbine #1, 100%
- Pengecekan (Perbaikan) gasket HPH Turbine #1, 100%
- Pengecekan (penggantian) manual gasket valve bypass Inlet Economizer di Elv. 7 dekat kamar mandi CCR, 100%
- Perbaikan Trafo 20KV, 85 %
- Cleaning Oil Cooler 1&2, 85 %
- Cleaning Air Cooler Generator, 100 %
- Start Turbine #1, 0%
Tanpa padam unit
- Cleaning sand filter, 80 %
- Perbaikan pondasi ring hammer, 25%
Additional work setelah stop unit#1
- Repair kebocoran deck area isolator ESP#1, 85%