Kondisi Pembangkit PLTU Baturaja 13 Desember 2023
Kondisi Operasi Mesin
STG 1 = ON (0 – 24)
STG 2 = OFF
Maintenance
Mekanik
- Repair ESP #2
Support electrical repair isolator Rod No.6
repair Hopper plate No.5 dan No.6
Repair deck isolator room - Cleaning Burner boiler #2
- Cleaning ducting PAF & SAF
- Repair Valve di Elv.32
- Pemindahan jip gantry dari sand filter #3 ke sand filter #1
- Melakukan perbaikan sand filter #1
- Repair kebocoran pada casing IDF #3 Dan #4
- Repair kebocoran bottom header pipa level drumb boiler#2
- Repair kebocoran valve superheater to sampling room
- Repair kebocoran gasket venting valve main desuperheater boiler#2
Elektrik
- Suport team subkon transformer
- Repair PC op#2
- Repair collecting elektrode Wsp#2
- Repair lighting area esp & idfan
- cek dan pengukuran busbar 380 V dan 6 KV
- Merger insulating main power transformer
SPB
1.konsumable OH unit#2 ( lokal)
Progres OH unit #2 PLTU baturaja 13 desember 2023
- Stop Boiler 2, 100 %
- Cooling boiler, ESP, drain debu ESP 2, 100%
- Cleaning ESP 2 (Drain), 90%
- Pengecekan Isolator dan Heater ESP 2 100 %
- Perbaikan Collecting Plate dan Elektroda, 50 %
- Perbaikan (penggantian) gasket manual valve Superheater Boiler #2 Elv. 32, 100%
- Perbaikan (penggantian) gasket manual valve Bypass MainSteam Boiler #2 Elv. 32, 100%
- Perbaikan (penggantian) manual valve venting MainSteam Boiler #2 Elv. 32, 100 %
- Pengecekan (perbaikan) Valve Steam Blow Boiler #2, 50%
- Pengecekan (perbaikan) sensor level Drum boiler 22, 50%
- Pengecekan Air Heater Boiler 2, 100%
- Cleaning Burner Boiler, 2, 100,%
- Cleaing Nozle Furnace Boiler 2, 100%
- Cleaing Nozle Solar Boiler. 0 %
- Start Boiler 2. 0%
TURBINE - Stop Turbine #2, 100%
- Pengecekan (Perbaikan) rembesan Oli Pilot Tranduser Turbine #2, 0%
- Pengecekan (penggantian) manual valve bypass Inlet Economizer di Elv. 7, 0 %
- Purifikasi & Perbaikan Trafo 20KV, 50 %
- Cleaning Oil Cooler 1&2, 0%
- Cleaning Air Cooler Generator 100%
- Start Turbine 2, 0 % TANPA PADAM UNIT
- Cleaning Sand Filter, 100 %
- Perbaikan Pondasi Ring Hammer, 65%
Additional work
- Repair deck plate area isolator Esp#2