Categories: PLTU BATURAJA

Kondisi Pembangkit PLTU Baturaja 15 Desember 2023

Kondisi Operasi Mesin
STG 1 = ON (0 – 24)
STG 2 = OFF

Maintenance
Mekanik

Agenda mekanik OH Boiler #2 Jumat 15 Desember 2023

  1. Repair ESP #2
    • Reposisi bottom pin Colecting Plate ruang no.6 baris 8 dan 10 dari manhole
    • Cleaning & Painting new plate deck isolator room
    • Covering ex repair dinding electroda room
    • close all manhole & bottom screen vessel tank
  2. Repair exhaust ducting boiler #2 Elv:0
  3. Melakukan penggantian packing fenting valve desuperheater stage #2
  4. Melakukan perbaikan/pengelasan plate strainer sand filter #1
  5. Melakukan improvemen jalur pipa udara untuk back wash pada sand filter #1
  6. Install pipa udara dari MPB ke WTP
  7. Flashing all H/E

Elektrik

  1. Support team subkon transformer#2
  2. Repair heater Esp#2, putus #1 unit
  3. Repair sensor sensor turbin#2
  4. Suport team mekanik

SPB
Nihil

Progres OH unit #2 PLTU baturaja 15 desember 2023

Stop Boiler 2, 100 %

  1. Cooling boiler, ESP, drain debu ESP 2, 100%
  2. Cleaning ESP 2 (Drain), 100%
  3. Pengecekan Isolator dan Heater ESP 2 100 %
  4. Perbaikan Collecting Plate dan Elektroda, 100 %
  5. Perbaikan (penggantian) gasket manual valve Superheater Boiler #2 Elv. 32, 100%
  6. Perbaikan (penggantian) gasket manual valve Bypass MainSteam Boiler #2 Elv. 32, 100%
  7. Perbaikan (penggantian) manual valve venting MainSteam Boiler #2 Elv. 32, 100 %
  8. Pengecekan (perbaikan) Valve Steam Blow Boiler #2, 95%
  9. Pengecekan (perbaikan) sensor level Drum boiler 22, 95%
  10. Pengecekan Air Heater Boiler 2, 95%
  11. Cleaning Burner Boiler, 2, 100,%
  12. Cleaing Nozle Furnace Boiler 2, 100%
  13. Cleaing Nozle Solar Boiler. 100 %
  14. Start Boiler 2. 0%
    TURBINE
  15. Stop Turbine #2, 100%
  16. Pengecekan (Perbaikan) rembesan Oli Pilot Tranduser Turbine #2, 95%
  17. Pengecekan (penggantian) manual valve bypass Inlet Economizer di Elv. 7, 100 %
  18. Purifikasi & Perbaikan Trafo 20KV, 95%
  19. Cleaning Oil Cooler 1&2, 95%
  20. Cleaning Air Cooler Generator 100%
  21. Start Turbine 2, 0 %
    TANPA PADAM UNIT
  22. Cleaning Sand Filter, 100 %
  23. Perbaikan Pondasi Ring Hammer, 80%

Additional work

  1. Repair deck plate area isolator Esp#2, 100 %
Muhammad Yusufi

Recent Posts

Kondisi Pembangkit PLTM Cibuni 22 Januari 2024

Kondisi Pembangkit PLTM Cibuni 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0-24)…

2 years ago

Kondisi Pembangkit PLTM Endikat 22 Januari 2024

Kondisi Pembangkit PLTM Endikat 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTM Lahat 22 Januari 2024

Kondisi Pembangkit PLTM Lahat 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTU Baturaja 22 Januari 2024

Kondisi Pembangkit PLTU Baturaja 22 Januari 2024 Kondisi Operasi Mesin STG 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTGU MUSI II 22 Januari 2024

Kondisi Pembangkit PLTGU MUSI II 22 Januari 2024 Kondisi Operasi Mesin GTG 1 = ON…

2 years ago

Kondisi Pembangkit PLTM Cibuni 21 Januari 2024

Kondisi Pembangkit PLTM Cibuni 21 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0-24)…

2 years ago