Kondisi Operasi Mesin
STG 1 = ON (0 – 24)
STG 2 = OFF
Maintenance
- Finishing repair dan hidrotest kebocoran pipa economizer dan desuperheater, 95%
- Additional work, repair main steam valve Boiler#2, 95%
SPB
Nihil
Progres OH unit #2 PLTU baturaja 17 Desember 2023
- Stop Boiler 2, 100 %
- Cooling boiler, ESP, drain debu ESP 2, 100%
- Cleaning ESP 2 (Drain), 100%
- Pengecekan Isolator dan Heater ESP 2 100 %
- Perbaikan Collecting Plate dan Elektroda, 100 %
- Perbaikan (penggantian) gasket manual valve Superheater Boiler #2 Elv. 32, 100%
- Perbaikan (penggantian) gasket manual valve Bypass MainSteam Boiler #2 Elv. 32, 100%
- Perbaikan (penggantian) manual valve venting MainSteam Boiler #2 Elv. 32, 100 %
- Pengecekan (perbaikan) Valve Steam Blow Boiler #2, 100%
- Pengecekan (perbaikan) sensor level Drum boiler 22, 100%
- Pengecekan Air Heater Boiler 2, 100%
- Cleaning Burner Boiler, 2, 100,%
- Cleaing Nozle Furnace Boiler 2, 100%
- Cleaing Nozle Solar Boiler. 100 %
- Start Boiler 2. 0%
TURBINE - Stop Turbine #2, 100%
- Pengecekan (Perbaikan) rembesan Oli Pilot Tranduser Turbine #2, 100%
- Pengecekan (penggantian) manual valve bypass Inlet Economizer di Elv. 7, 100 %
- Purifikasi & Perbaikan Trafo 20KV, 100%
- Cleaning Oil Cooler 1&2, 100%
- Cleaning Air Cooler Generator 100%
- Start Turbine 2, 0 %
TANPA PADAM UNIT - Cleaning Sand Filter, 100 %
- Perbaikan Pondasi Ring Hammer, 95%
Additional work
- Repair deck plate area isolator Esp#2, 100 %
- Repair kebocoran pipa economizer stelah hidrotest 95%
- Repair kebocoran pipa desuperheater setelah hidrotest
95%