Kondisi Operasi Mesin
STG 1 = ON (21.04 – 24.00)
STG 2 = ON ( 0 – 24 )
Maintenance
Mekanik
- Repair Ducting Burner Ignition Boiler#2 #A
- Centering support nozle ignition
- Cleaning Burner# B
- Pengecekan dumper valve Boiler#2 PAF ignition
- Refractory ducting burner
- Cleaning weighing
- Support team operation start-up unit#2
Elektrik
- engecekan termoucouple burner #A
- Suport team operation persiapan start-up unit#2
• SPB
Nihil
Progres OH unit #2 PLTU Baturaja 18 Desember 2023
BOILER
- Stop Boiler 2 100%
- Cooling Boiler, ESP, drain debu ESP 2 100%
- Cleaning ESP 2 (Drain) 100%
- Pengecekan Isolator dan Heater ESP 2 100%
- Perbaikan Collecting Plate dan Elektroda 100 %
- Perbaikan (penggantian) gasket manual valve Superheater Boiler 2 Elv. 32, 100%
- Perbaikan (penggantian) gasket manual valve Bypass MainSteam Boiler 2 Elv. 32 100%
- Perbaikan (penggantian) manual valve venting MainSteam Boiler 2 Elv. 32, 100%
- Pengecekan (perbaikan) Valve Steam Blow Boiler 2 100%
- Pengecekan (perbaikan) sensor level Drum Boiler 2 100%
- Pengecekan Air Heater Boiler 2, 100%
- Cleaning Burner Boiler, 2 100%
- Cleaing Nozle Furnace Boiler 2 100%
- Cleaing Nozle Solar Boiler 100 %
- Start Boiler 2. 100%
TURBINE - Stop Turbine #2 100%
- Pengecekan (Perbaikan) rembesan Oli Pilot Tranduser Turbine 2 100%
- Pengecekan (penggantian) manual valve bypass Inlet Economizer di Elv. 7 100%
- Purifikasi & Perbaikan Trafo 20KV 100%
- Cleaning Oil Cooler 1&2 100%
- Cleaning Air Cooler Generator 100%
- Start Turbine 2 100%
TANPA PADAM UNIT - Cleaning Sand Filter 100%
- Perbaikan Pondasi Ring Hammer 98%
ADDITIONAL WORK - Repair deck plate area isolator Esp#2 100%
- Perbaikan Crack dinding ESP#2 bagian atas 100%
- Perbaikan Casing Inveler IDFan 3 dan 4 100%
- Perbaikan valve Venting MOV 2 100%
- Penggantian gasket valve Superheater Boiler 2 100%
- Pengelasan valve sensor Level Drum bagian bawah sisi Mess 100%
- Repair kebocoran pipa economizer 95%
- Repair kebocoran desuperheater 100%
- Penggantian main steam motor valve MOV1 100%
- Repair kebocoran pipa drain colection header elv 7, 1titik 100%
- Penggantian valve colection header drain elv 7, 1 unit 100%
- Cleaning cyclone fluegas 100%
- Waterprofing deck rooftop ESP 2, 100%
38.Repair Heat exchanger PAF#2 Boiler#2, 100 % - Repair ducting Burner #A, 100 %
Alhamdulillah Overhaul Unit #1 dan #2 PLTU Baturaja sudah selesai secara keseluruhan