Kondisi Pembangkit PLTU Baturaja 18 Desember 2023

Kondisi Operasi Mesin
STG 1 = ON (21.04 – 24.00)
STG 2 = ON ( 0 – 24 )

Maintenance
Mekanik

  1. Repair Ducting Burner Ignition Boiler#2 #A
  2. Centering support nozle ignition
  3. Cleaning Burner# B
  4. Pengecekan dumper valve Boiler#2 PAF ignition
  5. Refractory ducting burner
  6. Cleaning weighing
  7. Support team operation start-up unit#2

Elektrik

  1. engecekan termoucouple burner #A
  2. Suport team operation persiapan start-up unit#2

• SPB
Nihil

Progres OH unit #2 PLTU Baturaja 18 Desember 2023

BOILER

  1. Stop Boiler 2 100%
  2. Cooling Boiler, ESP, drain debu ESP 2 100%
  3. Cleaning ESP 2 (Drain) 100%
  4. Pengecekan Isolator dan Heater ESP 2 100%
  5. Perbaikan Collecting Plate dan Elektroda 100 %
  6. Perbaikan (penggantian) gasket manual valve Superheater Boiler 2 Elv. 32, 100%
  7. Perbaikan (penggantian) gasket manual valve Bypass MainSteam Boiler 2 Elv. 32 100%
  8. Perbaikan (penggantian) manual valve venting MainSteam Boiler 2 Elv. 32, 100%
  9. Pengecekan (perbaikan) Valve Steam Blow Boiler 2 100%
  10. Pengecekan (perbaikan) sensor level Drum Boiler 2 100%
  11. Pengecekan Air Heater Boiler 2, 100%
  12. Cleaning Burner Boiler, 2 100%
  13. Cleaing Nozle Furnace Boiler 2 100%
  14. Cleaing Nozle Solar Boiler 100 %
  15. Start Boiler 2. 100%
    TURBINE
  16. Stop Turbine #2 100%
  17. Pengecekan (Perbaikan) rembesan Oli Pilot Tranduser Turbine 2 100%
  18. Pengecekan (penggantian) manual valve bypass Inlet Economizer di Elv. 7 100%
  19. Purifikasi & Perbaikan Trafo 20KV 100%
  20. Cleaning Oil Cooler 1&2 100%
  21. Cleaning Air Cooler Generator 100%
  22. Start Turbine 2 100%
    TANPA PADAM UNIT
  23. Cleaning Sand Filter 100%
  24. Perbaikan Pondasi Ring Hammer 98%
    ADDITIONAL WORK
  25. Repair deck plate area isolator Esp#2 100%
  26. Perbaikan Crack dinding ESP#2 bagian atas 100%
  27. Perbaikan Casing Inveler IDFan 3 dan 4 100%
  28. Perbaikan valve Venting MOV 2 100%
  29. Penggantian gasket valve Superheater Boiler 2 100%
  30. Pengelasan valve sensor Level Drum bagian bawah sisi Mess 100%
  31. Repair kebocoran pipa economizer 95%
  32. Repair kebocoran desuperheater 100%
  33. Penggantian main steam motor valve MOV1 100%
  34. Repair kebocoran pipa drain colection header elv 7, 1titik 100%
  35. Penggantian valve colection header drain elv 7, 1 unit 100%
  36. Cleaning cyclone fluegas 100%
  37. Waterprofing deck rooftop ESP 2, 100%
    38.Repair Heat exchanger PAF#2 Boiler#2, 100 %
  38. Repair ducting Burner #A, 100 %

Alhamdulillah Overhaul Unit #1 dan #2 PLTU Baturaja sudah selesai secara keseluruhan

Muhammad Yusufi

Recent Posts

Kondisi Pembangkit PLTM Cibuni 22 Januari 2024

Kondisi Pembangkit PLTM Cibuni 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0-24)…

2 years ago

Kondisi Pembangkit PLTM Endikat 22 Januari 2024

Kondisi Pembangkit PLTM Endikat 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTM Lahat 22 Januari 2024

Kondisi Pembangkit PLTM Lahat 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTU Baturaja 22 Januari 2024

Kondisi Pembangkit PLTU Baturaja 22 Januari 2024 Kondisi Operasi Mesin STG 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTGU MUSI II 22 Januari 2024

Kondisi Pembangkit PLTGU MUSI II 22 Januari 2024 Kondisi Operasi Mesin GTG 1 = ON…

2 years ago

Kondisi Pembangkit PLTM Cibuni 21 Januari 2024

Kondisi Pembangkit PLTM Cibuni 21 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0-24)…

2 years ago