Kondisi Pembangkit PLTU Baturaja 22 Desember 2023

Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON ( 0 – 24 )

Maintenance
Mekanik

  1. enggantian scrapper Exavator mini
  2. Inspeksi Conveyor weighing
  3. Fabrikasi portal untuk area DCS 1 arah tambang
  4. Inspeksi kompressor SULLAIR
  5. Repair Gearbox Rapping No.6
  6. Re install pipa udara dari MPB ke WTP
  7. Melanjutkan Fabrikasi maintenance dact vacoom valve turbine #2
  8. Melakukan penambahan oil IDF #2 dan IDF #4

Elektrik

  1. Kontinue repair motor Feed water pump #4
  2. Daily activities elektrik