Kondisi Pembangkit PLTU Baturaja 26 Desember 2023

Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON ( 0 – 24 )

Maintenance
Mekanik

  1. Penggantian scrapper Exavator mini
    Fabrikasi
  2. Inspeksi Conveyor weighing
  3. Inspeksi kompressor SULLAIR
  4. Repair T/V No. 4
    Ganti seal shaft pneumatic actuator
  5. Repair Gearbox Rapping No.6
    Trial & Install
  6. Repair kebocoran line transfer ash silo
    area atas vessel #6
  7. Ganti return roller B/C #1A
    Area crusher room Elv: 14.0

Elektrik

  1. Suport perbaikan AC 20 KV
  2. Suport instal gearbox rapping #6 Esp #2
  3. Perapian kabel Ethernet fingerprint pos Office Pltu
  4. Penambahan instalasi power gudang PLTU
  5. Daily activities elektrik

SPB

  1. Konsumable elektrik maintenance
Muhammad Yusufi

Recent Posts

Kondisi Pembangkit PLTM Cibuni 22 Januari 2024

Kondisi Pembangkit PLTM Cibuni 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0-24)…

2 years ago

Kondisi Pembangkit PLTM Endikat 22 Januari 2024

Kondisi Pembangkit PLTM Endikat 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTM Lahat 22 Januari 2024

Kondisi Pembangkit PLTM Lahat 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTU Baturaja 22 Januari 2024

Kondisi Pembangkit PLTU Baturaja 22 Januari 2024 Kondisi Operasi Mesin STG 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTGU MUSI II 22 Januari 2024

Kondisi Pembangkit PLTGU MUSI II 22 Januari 2024 Kondisi Operasi Mesin GTG 1 = ON…

2 years ago

Kondisi Pembangkit PLTM Cibuni 21 Januari 2024

Kondisi Pembangkit PLTM Cibuni 21 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0-24)…

2 years ago