Kondisi Pembangkit PLTU Baturaja 5 Januari 2024

Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON ( 0 – 24 )

Maintenance
Mekanik

  1. Fabrikasi jeep gantry sand filter WTP
  2. Melakukan perawatan pompa SC, SW dan back wash
  3. Flashing H/E feed pump
  4. Install gearbox rapping No.5
  5. Repair kebocoran line transfer ash silo
    Area vessel #1
    Area top main silo
  6. Inspeksi Weighing
  7. Inspeksi kompressor Sullair

Elektrik

  1. Perbaikan PS modul Ampere Gland Coolers T2.
  2. Perawatan Panel Trafo Ring Hammer Crusher
  3. Penambahan lampu di ashilo
  4. Perbaikan trafo las mekanik
  5. Daily maintenance

SPB
Nihil