Kondisi Pembangkit PLTU Baturaja 5 Januari 2024
Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON ( 0 – 24 )
Maintenance
Mekanik
- Fabrikasi jeep gantry sand filter WTP
- Melakukan perawatan pompa SC, SW dan back wash
- Flashing H/E feed pump
- Install gearbox rapping No.5
- Repair kebocoran line transfer ash silo
Area vessel #1
Area top main silo - Inspeksi Weighing
- Inspeksi kompressor Sullair
Elektrik
- Perbaikan PS modul Ampere Gland Coolers T2.
- Perawatan Panel Trafo Ring Hammer Crusher
- Penambahan lampu di ashilo
- Perbaikan trafo las mekanik
- Daily maintenance
SPB
Nihil