Kondisi Pembangkit PLTU Baturaja 10 Januari 2024

Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON ( 0 – 24 )

Maintenance
Mekanik

  1. nspeksi Weighing
    Lubiricating all rotary parts
    Cek splicing
    Cek hose power pack dumper #1
  2. Inspeksi kompressor Sullair
  3. P/M Ring hammer
    greasing all block bearing.
  4. Ganti carry roller B/C 1#B area bunker coal feeder
  5. Fabrikasi support manual valve cwp #1
  6. Melanjutkan install pipa jalur hydrolic pump CWP #1
  7. Flashing H/E feed pump
  8. Pengecatan maintenance dact vacoom valve turbine #2
  9. Melakukan pengecekan dan perawatan pompa dosing ammonia #1 dan #2

Elektrik

  1. Continue perbaikan hoise crane elv 14,5
  2. Penggantian lampu hopper weighing 1 dan 3
  3. Perawatan panel plc ESP
  4. perbaikan pressure gauge otlet cwp pump
  5. Daily maintenance

SPB
Nihil

Muhammad Yusufi

Recent Posts

Kondisi Pembangkit PLTM Cibuni 22 Januari 2024

Kondisi Pembangkit PLTM Cibuni 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0-24)…

2 years ago

Kondisi Pembangkit PLTM Endikat 22 Januari 2024

Kondisi Pembangkit PLTM Endikat 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTM Lahat 22 Januari 2024

Kondisi Pembangkit PLTM Lahat 22 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTU Baturaja 22 Januari 2024

Kondisi Pembangkit PLTU Baturaja 22 Januari 2024 Kondisi Operasi Mesin STG 1 = ON (0…

2 years ago

Kondisi Pembangkit PLTGU MUSI II 22 Januari 2024

Kondisi Pembangkit PLTGU MUSI II 22 Januari 2024 Kondisi Operasi Mesin GTG 1 = ON…

2 years ago

Kondisi Pembangkit PLTM Cibuni 21 Januari 2024

Kondisi Pembangkit PLTM Cibuni 21 Januari 2024 Kondisi Operasi Mesin Turbine 1 = ON (0-24)…

2 years ago