Kondisi Pembangkit PLTU Baturaja 8 Januari 2024
Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON ( 0 – 24 )
Maintenance
Mekanik
- nspeksi ESP
Cek Vessel #4
Reposisi gearbox rapping No.5 ke No.4
Ganti Gasket F/V No.6 - Inspeksi Weighing
- Inspeksi kompressor Sullair
- Cleaning
- Repair kebocoran line transfer ash silo
Area top mini silo
Area vessel #6 - Repair kebocoran ducting Hopper transfer B/C 1 A to R/S #A
- Melakukan perawatan all H/7. Melakukan perbaikan dosing pump biocide #2.
- Melakukan pengecatan jeep gantry
Elektrik
- Perawatan Panel Ring Hammer 1.a.
- Check Control Auto ESP, Botol 4.
- Perawatan greasing motor
- daily maintenance wtp area