Kondisi Pembangkit PLTU Baturaja 13 Januari 2024

Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON ( 0 – 24 )

Maintenance
Mekanik

  1. Inspeksi Weighing
    Cek splicing
  2. Inspeksi kompressor Sullair
    Support vendor perawatan 2000jam unit #1
    Cleaning
  3. Repair power pack hydraulic plough tripperNo.1 B/C #3
    Ganti rubber coupling
    repair skirt rubber 1.
  4. Repair H/E untuk spare H/E feed pump
  5. Cleaning area repair di CWP
  6. Flashing H/E feed pump
  7. Melakukan penambahan oil pada block bering idfan
  8. Abnormal ponton#1 cek dan repair

Elektrik

  1. .Perbaikan Control switch butterfly valve CWP 1.
  2. Perawatan Panel Switch Bunker DCS
  3. Charger accu genset Mpb
  4. Continue perbaikan hoise 14.5
  5. Daily dan perawatan maintenance
  6. Perbaikan main power office dan mess
  7. Abnormal motor ponton#1 cek dan repair

SPB
Nihil