Kondisi Pembangkit PLTU Baturaja 16 Juni 2023
Kondisi Operasi Mesin
STG 1 = ON 24 jam
STG 2 = OFF (0-11)
Kondisi Maintenance
Progres Overhaul hari ke 19
| Pekerjaan | Progress |
| A. Boiler 1 | 100% |
| Stop Boiler (100%) | 100% |
| Cooling Booiler, ESP, drain debu Esp 1 (100%) | 100% |
| Cleaning Esp 1 (100%) | 100% |
| Pengecekan Isolator dan Heater Esp 1 (75%) | 100% |
| Pengecekan dan perbaikan Collcecting Plate dan Elektroda Boiler 1 | 100% |
| Perbaikan kebocoran Ducting dan Bracing Esp 1 (15%) | 100% |
| Cleaning Air Heater Boiler 1 | 100% |
| Penggantian Shaft Rapping Vesel 1 | 100% |
| Penggantian Thermocouple Combution Boiler 1 | 100% |
| Pengecekan dan penggantian valve Collection Header Boiler 1 DN 80 & DN 20 | Proses |
| Pengecekan (perbaikan) sensor level drum Boiler 1 | 100% |
| Cleaning Burner Boiler 1 100% | 100% |
| Cleaning nozle Furnice Boiler 1 (70%) | 100% |
| Cleaning Nozle Solar Boiler 1 | 100% |
| Start Up Boiler 1 | 100% |
| B. Turbine 1 | |
| Stop Turbine 1 (100%) | 100% |
| Pengecekan Oli Governoor (50%) | 100% |
| Pengecekan Steam Room Governoor | 100% |
| Perbaikan sensor error di monitor CCR | 100% |
| Pengecekan (penggantian) Bearing Front Rear Turbine dan Generator (10%) | 100% |
| Set Aligment Shaft dan Coupling Turbine Generator | 100% |
| Perbaikan Flange gasket HPH Turbine 1 | 100% |
| Perbaikan pipa Drain main Steam Turbine 1 | 100% |
| Cleaning Condensore 1 (10%) | 100% |
| Cleaning Air Cooler 1 & 2 (100%) | 100% |
| Pengecekan dan Penggantian Bearing motor Exhaust Fan Turbine 1 | 100% |
| Pengecekan Generator STG 1 | 100% |
| Pengecekan Trafo STG 1 | 100% |
| Start Up Turbine 1 | 100% |
| C. Common | |
| Pengecekan (perbaikan) Bak Reservoir 2 & 3 (bocor/rembes) | 100% |
| Pengecekan (perbaikan) Corrosion Plate deck dan Handrill Cooling Tower | 42% |
| Pengecekan (perbaikan) System Sedimentasi | 100% |
| Perbaikan UPS | 100% |
| Perbaikan dan penggantian valve discharge main ash silo | 100% |
| Penggantian Filter udara Ash Silo | 100% |
| Perbaikan Mulut Hopper Crusher | Proses |
| Penggantian Belt Conveyor # 3 | 100% |
| Perbaikan Drive Pully Belt conveyor #2 | 100% |
| D. BOILER 2 | |
| Stop Boiler 2 | 100% |
| Cooling Booiler, ESP, drain debu Esp 1 | 100% |
| Cleaning Esp 1 | 100% |
| Pengecekan Isolator dan Heater Esp 1 | 100% |
| Pengecekan dan perbaikan Collcecting Plate dan Elektroda Boiler 1 | 100% |
| Perbaikan kebocoran Ducting dan Bracing Esp 1 | 100% |
| Cleaning Air Heater Boiler 1 | 100% |
| Repair flange gasket Front Desuperheater | 100% |
| Pengecekan dan Penggantian valve collection header boiler 2 DN 80 & DN 20 | Proses |
| Penggantian shaft rapping Vesel 4 | 100% |
| Repair Valve (Manual) Steam Blow Boiler 2 | 100% |
| Pengecekan (perbaikan) sensor level Drum boiler | 100% |
| Cleaning Burner Boiler 2 | 100% |
| Cleaning nozle Furnice Boiler 2 | 100% |
| Cleaning Nozle Solar Boiler 2 | 100% |
| Start Up Boiler 1 | Proses |
| E. Turbine 2 | |
| Stop Turbine 2 | 100% |
| Pengecekan Oli Governoor | 100% |
| Pengecekan Steam Room Governoor | 100% |
| Perbaikan sensor error di monitor CCR | 100% |
| Pengecekan (penggantian) Bearing Front Rear Turbine dan Generator | 100% |
| Set Aligment Shaft dan Coupling Turbine Generator | 100% |
| Perbaikan kebocoran MOV Turbine 2 di Elv 11,5 | Proses |
| Cleaning Condensore 2 | 100% |
| Cleaning Air Cooler 1 & 2 | 100% |
| Pengecekan dan Penggantian Bearing motor Exhaust Fan Turbine 2 | 100% |
| Pengecekan Generator STG 1 * | 90% |
| Pengecekan Trafo STG 1 | 100% |
| Start Up Turbine 1 | 100% |
-Nihil