Kondisi Pembangkit PLTU Baturaja 21 Agustus 2023
Kondisi Operasi Mesin
STG 1 = ON (0-24)
STG 2 = ON (0-24)
Maintenance
Mekanik
- Continue Fabrikasi drain manual silo mini
- Repair kebocoran jalur botol#6
- Repair transfer valve botol#5
- Cek auxiliary boiler & turbin
- Continue pengecekan ponton
- Continue finishing bongkar tripod kompresor #2 baru sulair
- Daily maintenance dan repair
Elektrik
- persiapan kabel power kompressor sulair 2
- continue greasing motor auxiliary
- repair selenoid esp 2
- perbaikan modul ampere panel wjt
- daily maintenance
SPB
Nihil