Kondisi Pembangkit PLTU Baturaja 25 September 2023
Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON (0 – 24 )
Maintenance
Mekanik
- Cleaning area work shop
- 2.Inspeksi Roller Screen 1 A (Vibrasi tinggi)
- Inspeksi ESP
Repair & Setting T/V No.2,3 dan 5 - PM. WTP
Fabrikasi kerangkeng box panel COS dan panel Jansen
Repair pintu Ponton dan pintu gerbang
Repair pompa SC #1
(Setting gland packing)
Lanjut install paranet area cooling tower. - PM.Boiler auxiliary
Elektrik
- Pernaikan panel Cos dan pemasangan led indikator ponton
- Continue support optimalisasi DCS
- Persiapan material perbaikan sapport kabel pltu ponton
- Daily motor auxiliary boiler