Kondisi Pembangkit PLTU Baturaja 27 September 2023
Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON (0 – 24 )
Maintenance
Mekanik
- Cleaning area work shop
- Inspeksi ESP vessel tank #1
- PM. WTP
Fabrikasi kerangkeng box panel COS dan panel Jansen
Repair pintu Ponton dan pintu gerbang
Cleaning screen foot valve & Y Screen
Lanjut install paranet area cooling tower arah CWP - PM. All pumps
- Repair kebocoran line transfer ash silo
- Fabrikasi rack spare parts logistic
- Inspeksi Weighing #1
Elektrik
- Terminasi couple kabel pltu ke COS
- pengelasan dudukan kabel pltu ponton
- Support optimalisasi hoist crane DCS
- Daily maintenance
SPB
Plate hardock 500 2500X6000xX600 ( pusat)