Kondisi Pembangkit PLTU Baturaja 7 Oktober 2023

Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON (0 – 24 )

Maintenance
Mekanik

  1. Cleaning area work shop dan Senam Pagi
  2. PM Kompresor SULLAIR
    Cleaning room ( vaccum cleaner )
  3. Inspeksi All Weighing conveyor
  4. Repair SC Pumps #1
  5. Repair Drive Pulley Conveyor
    -Dismantling planetary gear
  6. Repair maint. dact dan tangga WTP.
  7. Melakukan penambahan oil block bearing IDF.

Elektrik

  1. Senam pagi
  2. perbaikan selang selenoid ash silo
  3. Perawatan screen fan motor auxiliary
  4. perbaikan kontrol ICP das Wtp
  5. Daily maintenance