Kondisi Pembangkit PLTM Endikat 24 Oktober 2023
Kondisi Operasi Mesin
Turbine 1 = ON (0-17)
Turbine 2 = ON (0-1)
Turbine 3 = ON (0-8)
SPB
Nihil
Maintenance
Penimbunan Di area HP
Pembanguan sidedicht sta 500
Monitoring All Power Plant Manggala
Kondisi Operasi Mesin
Turbine 1 = ON (0-17)
Turbine 2 = ON (0-1)
Turbine 3 = ON (0-8)
SPB
Nihil
Maintenance
Penimbunan Di area HP
Pembanguan sidedicht sta 500