Kondisi Pembangkit PLTU Baturaja 7 November 2023
Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON (0 – 24 )
Maintenance
Mekanik
- Cleaning area workshop
- Inspeksi All Weighing conveyor
- Inspeksi kompresor SULLAIR
- Fabrikasi doubling plate elbow Ash silo
- PM WTP
Melakukan pengecekan dan perawatan Unit R/O #1A, R/O 1B, R/O 2A dan R/O 2B.
Melakukan pengecekan dan perawatan pada pompa waterpont.
Melakukan penggantian frame dan plate bordes lantai WTP. - Repair spare Block bearing R/S
Elektrik
- Lepas kabel power dan chek insulating spool Cwp 1
- Perbaikan kontrol roller screen 2 Crusher
- .Perawatan grounding demin
- Daily maintenance
SPB
Nihil