Kondisi Pembangkit PLTU Baturaja 8 November 2023

Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON (0 – 24 )

Maintenance
Mekanik

  1. Cleaning area workshop
  2. Inspeksi All Weighing conveyor
  3. Inspeksi kompresor SULLAIR
  4. .Repair kompresor FEIHE NO.#2 ( Indikasi bearing screw jaming )
    Dismantling All parts & Cleaning
  5. Fabrikasi doubling plate elbow Ash silo (Elbow Manganese Steel)
  6. PM WTP
    Melakukan perawatan dan pengecekan cooling fan all.
    Melakukan penggantian plate bordes lantai WTP.
  7. Repair bocor line transfer Ash silo.
  8. Repair bocor ducting hopper transfer R/S #1B
  9. Repair ESP Vessel Tank #5 ( Indikasi losses Pressure )
    Repair bottom screen
    Repair membrane pressure gauge

Elektrik

  1. Pengecekan unit AC 20 KV
  2. Pengecekan dan bongkar power meter STG#1 Abnormal ( rusak)
  3. Kontinue repair kabel power motor CWP#1
  4. Pengecekan kabel intake ponton dari Rumah genset samping rel kereta Api

SPB
Nihil